To increase performance the Interxion Deutschland GmbH data centre, SWR GmbH was contracted to carry out excavation and pipe construction work for a new 30kV medium-voltage line plus pipe construction work to lay additional signal cables in the existing data centre.
Expanding fully occupied cable ducts during ongoing operations presented a particular challenge. They needed to be expanded to increase capacities in transmission paths.
- Customer:
- InterXion
- Place of execution:
- Rhine-Main region
- Duration of project:
- On-going
- Execution:
- Südwestdeutsche Rohrleitungsbau GmbH