Equinix
Civil engineering and surface works were carried out and protective cable duct routes (around 310 x 8 m KSR da160, around 170 x 10 m KSR da110) laid during construction of the data centre for client Equinix.
The route needed to pass under a supply duct to connect the route to the transformer rooms. This was achieved using the moling method to lay DN 200 steel pipes with the soil removed using high-pressure flushing.
A line connection was made on the premises to supply the data centre with electricity. Protective cable ducts were also laid (around 120 x 16 m da125) for this purpose.
- Customer:
- Equinix Germany GmbH
- Place of execution:
- Frankfurt am Main
- Duration of project:
- May 2017 – November 2017
- Execution:
- Südwestdeutsche Rohrleitungsbau GmbH
- Contract value:
- 0.64 Mio. EUR