Drinking water pipeline in Bischofsheim
We carried out welding work on a DN 800 steel drinking water pipeline over a 1000 m section for Keil und Purkl Tiefbau GmbH in Bischofsheim in the Mainz region.
The existing, ageing drinking water transmission pipeline was removed and replaced with a new one. In order not to interrupt the drinking water supply during the construction work, a d630 PE bypass needed to be laid before decommissioning.
A railway line needed to be crossed in an existing tunnel structure in one section.
- Customer:
- Keil und Purkl Tiefbau GmbH
- Place of execution:
- Mainz-Bischofsheim
- Duration of project:
- August 2019 - May 2020
- Execution:
- Südwestdeutsche Rohrleitungsbau GmbH
- Contract value:
- 0.24 Mio. EUR